Rapid Easter and Summer-holiday crane installation

Stock and refurbished classrooms deploy in 4 to 8 weeks when concrete pads and ducts finish beforehand, letting mobile cranes lift 1 to 6 units safely over Easter or July–August holidays.

How Irish schools schedule surveys, foundations, FSC/DAC sign-off and mobile crane lifts during holiday breaks so September classes open on time.

Free, no obligation. One local supplier prices it, not five.

  • 4 to 8 weeksstock/refurb prefab to handover
  • 1 to 2 dayscrane lift for 1 classroom unit
  • 4 to 7 dayscrane lift for 4–6 unit wing
  • July & Augustpeak Irish school crane window
Yellow construction crane boom and steel lifting hook suspended against an overcast grey sky

Working backwards from the first day of term

Irish schools have three narrow empty-yard windows each year: the two-week Easter break, October and February mid-terms, and the July–August summer holiday. Lifting 8-tonne to 14-tonne modular sections over perimeter walls while 400 pupils are on campus is rarely permitted under site safety rules, so hitting a summer crane slot requires locking in approvals and groundworks months ahead.

September (stock hire / refurb)

Order & survey cutoff
April to mid-May
Pads, ducts & FSC/DAC
May to late June (outside school hours)
Crane lift & commissioning
July crane lift, August commissioning & snagging

September (4–12 room new block)

Order & survey cutoff
November to February prior
Pads, ducts & FSC/DAC
Spring civils & BCMS filings
Crane lift & commissioning
Early July crane assembly, August M&E fit-out

Post-Easter term (stock unit)

Order & survey cutoff
January to mid-February
Pads, ducts & FSC/DAC
February mid-term pad pour
Crane lift & commissioning
Easter 2-week holiday lift, link-up & handover

Emergency mid-year decant

Order & survey cutoff
Immediate yard call-off
Pads, ducts & FSC/DAC
Weekend pad prep + hoarding
Crane lift & commissioning
Mid-term break or Saturday–Sunday crane lift

Stock and refurbished hire fleets move far faster than bespoke factory builds because the steel shells already exist in an Irish depot. Even so, crane operators book solid for July and August by late spring, and ESB Networks load upgrades cannot be rushed in three weeks.

Price my units

Four quick taps show Irish unit hire or capital guides before asking for a contact number. One local supplier prices it, not five.

Temporary prefab classroom hire, 2 to 3 units, 12 to 24 month lease: €1,000 to €2,550/wk ex VAT plus €26,000 to €48,000 one-off delivery, crane & removal.

Step 1 of 5

What kind of classroom units do you need?

Pick the closest fit. A supplier checks yard levels and tie-ins on site.

How the unit guide is worked out

Weekly hire bands reflect standard Irish 12 to 24 month and 36+ month education lease rates per classroom module, excluding VAT (23% on rental). One-off mobilisation and demobilisation covers low-loader haulage, mobile crane lifts, concrete pad setup and end-of-lease removal. Refurbished capital ranges cover pre-owned stock units overhauled before delivery. New turnkey ranges reflect multi-unit Irish school block pricing at €2,300 to €3,500/m² ex VAT (13.5% VAT on qualifying supply-and-fit construction). ESB Networks three-phase upgrades, foul pump stations and link corridors depend on yard survey.

What your supplier checks during the pre-crane yard survey

  1. Gate pier width and approach road swept path. Standard modular bays travel 3.2 m to 4.2 m wide on 16.5 m articulated trailers. Tight village corners, parked cars or low stone pillars dictate bay width and escort permits.
  2. Overhead ESB lines and telecom cables. Any overhead conductors crossing the crane slew radius must be shrouded, disconnected temporarily or avoided by relocating the crane pad.
  3. Underground drains and septic tanks under outriggers. An 80-tonne to 160-tonne mobile crane exerts huge point loads through its four outriggers; manholes, soft playfields and attenuation tanks require engineered spreader mats.
  4. Pre-cured concrete pads and live service tails. Concrete foundations need 7 to 14 days curing before bearing modular bays, with armoured power, water, foul and data ducts stubbed cleanly inside the pad footprint.

Review utility lead times early on three-phase ESB and foul drainage tie-ins.

Common questions from school boards

How early do we need to order for a September classroom opening?

For stock hire or refurbished prefabs, aim to sign by April or mid-May so FSC/DAC filings, concrete pads and July crane slots are secured. For bespoke multi-storey blocks, start between November and February.

Can classrooms be craned in during the two-week Easter holiday?

Yes for 1 to 3 stock or refurbished units, provided concrete pads, drainage and power ducts are poured beforehand so crane assembly takes just 1 to 2 days to 2 to 4 days.

What happens if high winds hit on our scheduled crane day?

Safe crane lifting pauses when sustained gusts exceed roughly 30 to 35 km/h because wide modular bays catch wind like sails. Always build a 3 to 5 day weather float into holiday lift plans.

How long does commissioning take after the crane leaves?

Allow 1 to 2 weeks for single-storey stock units (joint sealing, power/data tie-in, ramp bolting, fire-alarm testing) and 3 to 5 weeks for multi-storey blocks.

Every modular classrooms guide and county page

modularclassrooms.ie is an independent Irish information site. It is not affiliated with the Department of Education, the NCSE or any local authority, and does not allocate school capital or hire grants.

Two-storey modern school campus building with grid windows, gravel footpath and staked young trees on a green lawn