Rapid Easter and Summer-holiday crane installation
Stock and refurbished classrooms deploy in 4 to 8 weeks when concrete pads and ducts finish beforehand, letting mobile cranes lift 1 to 6 units safely over Easter or July–August holidays.
How Irish schools schedule surveys, foundations, FSC/DAC sign-off and mobile crane lifts during holiday breaks so September classes open on time.
Free, no obligation. One local supplier prices it, not five.
- 4 to 8 weeksstock/refurb prefab to handover
- 1 to 2 dayscrane lift for 1 classroom unit
- 4 to 7 dayscrane lift for 4–6 unit wing
- July & Augustpeak Irish school crane window

Working backwards from the first day of term
Irish schools have three narrow empty-yard windows each year: the two-week Easter break, October and February mid-terms, and the July–August summer holiday. Lifting 8-tonne to 14-tonne modular sections over perimeter walls while 400 pupils are on campus is rarely permitted under site safety rules, so hitting a summer crane slot requires locking in approvals and groundworks months ahead.
September (stock hire / refurb)
- Order & survey cutoff
- April to mid-May
- Pads, ducts & FSC/DAC
- May to late June (outside school hours)
- Crane lift & commissioning
- July crane lift, August commissioning & snagging
September (4–12 room new block)
- Order & survey cutoff
- November to February prior
- Pads, ducts & FSC/DAC
- Spring civils & BCMS filings
- Crane lift & commissioning
- Early July crane assembly, August M&E fit-out
Post-Easter term (stock unit)
- Order & survey cutoff
- January to mid-February
- Pads, ducts & FSC/DAC
- February mid-term pad pour
- Crane lift & commissioning
- Easter 2-week holiday lift, link-up & handover
Emergency mid-year decant
- Order & survey cutoff
- Immediate yard call-off
- Pads, ducts & FSC/DAC
- Weekend pad prep + hoarding
- Crane lift & commissioning
- Mid-term break or Saturday–Sunday crane lift
Stock and refurbished hire fleets move far faster than bespoke factory builds because the steel shells already exist in an Irish depot. Even so, crane operators book solid for July and August by late spring, and ESB Networks load upgrades cannot be rushed in three weeks.
Price my units
Four quick taps show Irish unit hire or capital guides before asking for a contact number. One local supplier prices it, not five.
Temporary prefab classroom hire, 2 to 3 units, 12 to 24 month lease: €1,000 to €2,550/wk ex VAT plus €26,000 to €48,000 one-off delivery, crane & removal.
How the unit guide is worked out
Weekly hire bands reflect standard Irish 12 to 24 month and 36+ month education lease rates per classroom module, excluding VAT (23% on rental). One-off mobilisation and demobilisation covers low-loader haulage, mobile crane lifts, concrete pad setup and end-of-lease removal. Refurbished capital ranges cover pre-owned stock units overhauled before delivery. New turnkey ranges reflect multi-unit Irish school block pricing at €2,300 to €3,500/m² ex VAT (13.5% VAT on qualifying supply-and-fit construction). ESB Networks three-phase upgrades, foul pump stations and link corridors depend on yard survey.
What your supplier checks during the pre-crane yard survey
- Gate pier width and approach road swept path. Standard modular bays travel 3.2 m to 4.2 m wide on 16.5 m articulated trailers. Tight village corners, parked cars or low stone pillars dictate bay width and escort permits.
- Overhead ESB lines and telecom cables. Any overhead conductors crossing the crane slew radius must be shrouded, disconnected temporarily or avoided by relocating the crane pad.
- Underground drains and septic tanks under outriggers. An 80-tonne to 160-tonne mobile crane exerts huge point loads through its four outriggers; manholes, soft playfields and attenuation tanks require engineered spreader mats.
- Pre-cured concrete pads and live service tails. Concrete foundations need 7 to 14 days curing before bearing modular bays, with armoured power, water, foul and data ducts stubbed cleanly inside the pad footprint.
Review utility lead times early on three-phase ESB and foul drainage tie-ins.
Related modular unit guides
Decant classrooms for rebuildsKeeping every class teaching on site during roof replacements, extensions and M&E upgrades.
Temporary prefab classroom hireWeekly lease rates for 12, 24 and 36 month terms plus honest crane and removal costs.
Multi-classroom 2-storey blocks4 to 12 room school campus wings with stairs, lifts, circulation and turnkey €/m² rates.
Relocation, removal & reinstatementMoving existing prefabs, reversing crane lifts and restoring school tarmac or grass.
Three-phase ESB & foul drainageESB Networks IMIC load applications, three-phase sub-mains and gravity vs pumped foul tie-ins.
FSC, DAC, ramps & link corridorsFire Safety Certificates, Disability Access Certificates, ramps and covered school walkways.Common questions from school boards
How early do we need to order for a September classroom opening?
For stock hire or refurbished prefabs, aim to sign by April or mid-May so FSC/DAC filings, concrete pads and July crane slots are secured. For bespoke multi-storey blocks, start between November and February.
Can classrooms be craned in during the two-week Easter holiday?
Yes for 1 to 3 stock or refurbished units, provided concrete pads, drainage and power ducts are poured beforehand so crane assembly takes just 1 to 2 days to 2 to 4 days.
What happens if high winds hit on our scheduled crane day?
Safe crane lifting pauses when sustained gusts exceed roughly 30 to 35 km/h because wide modular bays catch wind like sails. Always build a 3 to 5 day weather float into holiday lift plans.
How long does commissioning take after the crane leaves?
Allow 1 to 2 weeks for single-storey stock units (joint sealing, power/data tie-in, ramp bolting, fire-alarm testing) and 3 to 5 weeks for multi-storey blocks.
Every modular classrooms guide and county page
Units & campus blocks
Hiring, crane & compliance
Regional logistics
modularclassrooms.ie is an independent Irish information site. It is not affiliated with the Department of Education, the NCSE or any local authority, and does not allocate school capital or hire grants.

Check your unit rate before anyone phones
Pick the unit format, room count and hire or purchase route. When you want a site-verified quotation, your outline reaches a single local modular supplier in your county.